Well…… the progress has been amazing. Since our last update the contractor’s forces have poured the concrete slabs (Devencenzi) for all three buildings, erected a portion of the wood walls (Archer) and the structural steel (Hilo Erectors) for the main building. before Christmas Sundt expects to have all of the wood framed roofs up and roofing on. This is a good thing, since we have been lucky so far that our typical winter weather has held! We will also see the metal decking finalized and the concrete put on at the second floor.
Yuba Community College – Clearlake Campus – Student Services Center
October 6, 2011After a wet spring and a mild summer we have now completed “Increment 1 – Site Package” for the Yuba Community College Student Services Center. The program is incorporated into three buildings and is quite varied, combining Administration Services, Learning Resource Center and Career Center, Library, Culinary Arts, and Science Clasrooms (including a Cadaver Room for Anatomy classes). The design team has worked closely with Sundt Construction to meet a schedule of preparing the site building pads, adding Rammed Aggregate Piers, and providing new parking and fire access roads, ahead of the Fall semester, which started in late September. The second part of the project: Increment 2 – Building Package was approved by the Division of the State Architect and as of late September is well under way. The footings have been poured and we are moving quickly toward the slab on grade pours. After that, the students and staff will start to see steel and wood framing for the walls. The project is scheduled for completion in summer 2012, so that the Owner can take occupancy in the Fall of 2012.
DeTurk Round Barn Continued Progress – “Raising the Roof”
August 11, 2010Now that the DeTurk Round Barn has been lowered onto the new concrete curb and post-tension slab the work of replacing the roof has begun. The skip sheathing creates a wonderful pattern in its exposed state (unfortunatley keeping it this way would not work so well in our rainy winters). Once the shingles are in place the installation of the “Big Ass Fan” (24 feet in diameter!) will commence. You can see, in one image, that the center portion of the slab is ready for the concrete pour, with rebar and radiant tubing in place. The wood framing is well underway, with the studs, joists, and wall framing happening. GCCI, the general contractor, is doing an amazing job at juggling the complex issues associated with transforming a 119 year old barn to function in the 21st century.
DeTurk Round Barn Renovation Update
May 27, 2010Well, the DeTurk Round Barn Renovation (for the City of Santa Rosa – Recreations and Parks Department) is underway. As you can see from the photos the Dog Park is nearing completion and preparations for the lifting of the Barn are under way. The Dog Park is a very important part of this project, being a very popular meeting place for local (West End Historic Neighborhood) and city wide residence. The barn is being lifted approximately 3 feet. This will provide clearance to prepare column footings and elevator pit, place underslab electrical conduit and work on a post tension concrete slab (more information and photos in a future blog). The barn will then be lowered onto a new concrete curb. Note all of the beams running through the existing window openings. The windows are being reconditioned (to maintain historic elements) and will be replaced after the lifting is complete.
Once the building is lowered the General Contractor (GCCI Inc.) will begin interior work in earnest………….Stay Tuned






Posted by kevinteel 
















